The 2nd China International Import Expo Lifting Points Use Manual Release date: 2019-08-02

Click to download

I. General

This section mainly introduces the parameters of lifting points in exhibition hall, the applicable scope of lifting point service, as well as its standard and process.

Shanghai High-fair Advertising & Engineering Co., Ltd. is the lifting point service provider designated by China International Import Expo this year.

Shanghai High-fair Advertising & Engineering Co., Ltd.

Address4th Floor, 3 Hall, No.1988, Zhuguang Rd., Qingpu District, Shanghai, China

Contact: Ryan Chen

Tel: 86-21-69761559

Mobile: 86-13610041071

Contact: Varus Zhang

Tel:86-21-69761559

Mobile: 86-18936756321

E-mailhf1@cantonfairad.com

All booths applying for the lifting point service shall follow the requirements on booth design and construction stipulated in the Exhibitor Manual of China International Import Expo, this Manual and other relevant regulations.

Applications for lifting point service should be made in advance according to the declaration time, and all on-site applications with drawings will not be accepted after move-in.

Users who apply for the lifting point service shall rent the hoist equipment uniformly provided by the exhibition hall and not use self-prepared hoists.

National Convention and Exhibition Center (Shanghai) Co., Ltd. reserves the right of final interpretation.

II. Scope of Application

Lifting point service of the 2nd China International Import Expo is available in the North Hall (N Hall) of the National Convention and Exhibition Center (Shanghai), the first floor of the double-deck exhibition hall (Hall 4.1, Hall 5.1, Hall 6.1, Hall 7.1, Hall 8.1) and the second floor of the double-deck exhibition hall (Hall 6.2, Hall 7.2, Hall 8.2), while is unavailable in Hall 1.1, Hall 1.2, Hall 2.1, Hall 2.2, Hall 3 and Hall 5.2 in the National Convention and Exhibition Center (Shanghai).

Lifting point hangings: lighting fixtures, projectors, light boxes, signboards, ceilings, as well as trusses and metal frame structures where the above equipment are hung.

Lightweight hanging flags for advertising purpose (including but not limited to print cloth, grid cloth, removable back glue and light cloth) do not fall into the range of lifting point service, and shall still comply with the exhibition hall advertising operation plan.

The lifting point service provider is responsible for providing the lifting points, installing the hoists connecting the lifting points and retracting the chains.

Hoist equipment must be uniformly rented from the exhibition hall. The user may prepare Truss racks connecting the hangings and lifting points or apply to the hall owner for rental.

Hangings shall be prepared and assembled by the user of the lifting point.

 

III. Parameters of Lifting Points

Hall No.

Hall 4.1/ Hall 5.1/Hall 6.1/Hall 7.1/Hall 8.1

Hall 6.2/Hall 7.2/Hall 8.2

North Hall

Lifting point load

≤150kg

Single structure load limit

≤900kg

Single structures exceeding the load limit must be disintegrated for hoisting

Height of one-layer main rack

━━

17m

17m

Height of two-layer main rack

12m

12m

━━

Height limit of hangings

Ground clearance of upper edge of the hanging≤8.5m

Note: For single structure exceeding the weight limit, lifting points shall be increased in accordance with the regulations.

 

Schematic Diagram of Lifting Point System of Exhibition Hall

The red Truss rack is a one-layer main rack, and the blue Truss rack is a two-layer main rack.


TIM图片20190802183006.jpg

IV. Charging Standards

ICharging standard of lifting point service

Item

Specification

Unit Price (RMB Yuan)

Notes

Lifting point

Lifting point

RMB 3000 Yuan/point/exhibition period (event period)

Application with drawing is not accepted after the deadline

Hoist rental

Chain hoist, 15-meter chain, 1 ton

RMB 450 Yuan/piece

Chain hoist, 25-meter chain, 1 ton

RMB 675 Yuan/piece

Electric hoist, 15-meter chain, 1 ton

RMB 1,800 Yuan/piece

Electric hoist, 25-meter chain, 1 ton

RMB 2,250 Yuan/piece

Notes:

1. The user who applies for the lifting point service shall rent the hoist equipment uniformly provided by the exhibition hall.

2. Lifting point service fee consists of lifting point fee and hoist rental service fee, including chain retracting service and hoist electricity fees; excluding Truss rack rental fee.

3. Lifting point service fee shall be paid to the hall owner 15 days before move-in, and the hall owner will arrange the order on the system for installation after confirming the receipt of the payment.

4. The hoist rental service includes hoist rental and installation.

5. For the deadline for applying for lifting points, please refer to the relevant requirements in V. Lifting Point Service Application Process and Related Requirements.

 

IIEquipment rental charging standard

Item

Name/Specification

Unit Price (Yuan)

(RMB/Exhibition Period/Event Period)

Truss rack rental

Truss rack (original aluminum color) 300*300

150 Yuan/m

Truss rack (original aluminum color) 400*400

225 Yuan/m

Truss rack (original aluminum color) 400*600

270 Yuan/m

Truss rack (original aluminum color) 600*700

300 Yuan/m

Notes:

1. Truss rack rental service includes rack and related spare and accessory parts required for assembly, Truss rack assembly and installation.

2. The rental length of the Truss rack is uniformly rounded in meters.

3. Equipment rental fee shall be paid to the hall owner 15 days before move-in, and the hall owner will arrange the order on the system and prepare the equipment after confirming the receipt of the payment.


V. Lifting Point Service Application Process and Related Requirements

(I) Lifting point service application process



 TIM图片20190802172402.png

(II) Requirements related to application for lifting point service

l The user of the lifting point must submit an application for hoisting point service or equipment rental 30 natural days before move-in, and submit the initial data (electronic version) for audit at the same time; The number of lifting points, the point positions or the quantity of rented equipment shall be confirmed 15 natural days before move-in, and the confirmed data for audit (one stamped paper version) shall be submitted to the service provider, and applications with drawings shall not be accepted after the deadline.

l All on-site applications with drawings after move-in will not be accepted.

l For applications submitted for equipment rental after the deadline, the information must be approved by the hall owner and feasibility of implementation on the site be confirmed before placing the order.

l List of information required for applying for lifting point service:

No.

Category

Remarks

1

Confirmation Form of Lifting Point Service in Exhibition Hall

See Table 1 for details. A confirmed paper version with a seal must be submitted.

2

Letter of Undertaking on Application for and Use of Lifting point Service in Exhibition Hall

See Table 2 for details. A confirmed paper version with a seal must be submitted.

3

Point Position Distribution and Material Description Map

The map shall be drawn according to the plan of the booth, and it is necessary to clearly indicate the locations of all hoisting structures, the lifting points used and the locations of facilities and equipment fixed to the structures, the size and weight of each structure, as well as the models, specifications, quantity, and self-weight of equipment on the structures, as shown in Figure 3.

4

Effect Drawings

Provide the front elevation effect drawing, the side elevation effect drawing, the top view drawing and the overall effect drawing of at least two angles of the booth, as shown in Figure 4. A confirmed paper version with a seal must be submitted.

 

l Once all the drawings of lifting plan are approved, the construction must be carried out on the site in accordance with the confirmed plan. If it is found that the lifting points on the site have not been constructed in accordance with the original submitted plan, or the weight of hanging exceeds the declared value, the hall owner and the service provider have the right to stop the on-site construction, and the applicant shall increase the number of lifting points or reduce the weight of hanging as required.

l The cost of rectification caused by reasons such as the constructor's failure to implement according to the declared weight shall be borne by the constructor itself.

VI. Requirements Related to Use of Lifting Points

l If the weight of a single hanging exceeds the total load of the lifting point applied for, the user must apply for an increase in the number of lifting points.

l Steel-core steel wires or special lifting straps must be used to connect independently and vertically with the lifting points provided by the exhibition hall service provider, and comply with the height limit of structure lifting.

l Hangings lifted through the lifting point must be of a solid and reliable metal or steel wood assembly structure. It is not allowed to lift pure wood structure, subwoofer speakers and linear array speakers. For structures that are connected to the ground or do not rely on the lifting point to bear load, it is strictly prohibited to use any lifting point for reinforcement or connection.

l If a single structure lifted through the chain hoist has 6 or more lifting points, it needs to be disintegrated for lifting; if the structure cannot be disintegrated for lifting, it needs to be lifted with an electric hoist.

l All lighting fixtures must be constructed according to the distribution map made at the time of application, and another application for drawing examination is required in case of any change.

l After the user's hangings have been assembled, they can be suspended only after being inspected by the service provider. The hangings lifted by electric hoist shall be arranged by the service provider; the hangings of chain hoist shall be lifted by the user.

l Before using a chain hoist, the user must notify the service provider and lift the hanging under the on-site supervision of the service provider.

l During the rise or decline of the hoist, force must be balanced at each point of the structure, and each hoist must rise or fall synchronously to avoid lack of force at individual or partial positions.


Table 1: Confirmation Form of Lifting Point Service in Exhibition Hall

Application Unit:

Applicant:

Contact Method:

 

No.

Booth No.

Company Name

Nature of booth (special/standard)

Area

Person in Charge

Contact Phone

Exhibition Hall Lifting Points

Equipment Rental

Lifting points

(pcs)

Truss rack 300*300 (m)

Truss rack 400*400 (m)

Truss rack 400*600

(m)

Truss rack 600*700 (m)

Chain hoist, 15-meter chain, 1 ton

(pcs)

Chain hoist, 25-meter chain, 1 ton

(pcs)

Electric hoist, 15-meter chain, 1 ton

(pcs)

Electric hoist, 25-meter chain, 1 ton

(pcs)

1

2

3

4

5

TOTAL

0

0

0

0

0

0

0

0

0

Unit price:

3,000.00

150.00

225.00

270.00

300.00

450.00

675.00

1,800.00

2,250.00

Subtotal:

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

Total:

0.00

Note: The rental length of the Truss rack is uniformly rounded in meters.

National Convention and Exhibition Center (Shanghai) Co., Ltd. (Signed by the confirmation person, affixed with the official seal of the company):

Applicant unit (Signed by the confirmation person, affixed with the official seal of the company):

Shanghai High-fair Advertising & Engineering Co., Ltd. (Signed by the confirmation person, affixed with the official seal of the company):

 


Table 2: Letter of Undertaking on Application for and Use of Lifting Point Service in Exhibition Hall

 

Letter of Undertaking on Application for and Use of Lifting Point Service in Exhibition Hall

 

In order to implement the policy of "people-oriented, safety first" and ensure the safety of exhibition activities in accordance with relevant laws and regulations, we have made the following safety undertaking in the process of applying for and using lifting point service:

 

Article 1 Person in charge of the safety of lifting point

We have made it clear that

Name:                        

ID card number:

Contact mobile phone:          

is the person in charge of lifting point safety for Booth No.:

of this exhibition/event.

 

Article 2 Items of Undertaking

1. We undertake that the information we submitted for examination is authentic and reliable.

2. We undertake to be responsible for the safety of free property and our own workers, purchase insurance for them and provide necessary qualified labor protection appliances for construction safety, and ensure that the relevant workers wear safety helmets in the exhibition hall during the construction and move-out.

3. We undertake to improve the safety education for construction personnel, and not to arrange work to construction personnel who have not received safety education, technical training and failed to pass the examination.

4. We undertake to ensure that the personnel engaged in aerial work are trained by the safety production supervision or quality and technology supervision departments and work with a certificate.

5. We undertake to be responsible for ensuring construction safety and protection facilities, and take measures to prevent high-altitude falls and injury due to falling objects.

6. We undertake that all of our equipment, facilities, parts, components and other related materials are safe and reliable, conforming to the mandatory standards of relevant laws and regulations.

7. We undertake to accept the safety inspection of the construction site by the lifting point service provider and various departments of the exhibition hall, comply with their arrangements and eliminate unsafe factors in a timely manner, put an end to potential accidents and hidden dangers, prevent and avoid personal injury accidents.

8. We undertake to abide by the Exhibitor Manual of China International Import Expo and other relevant safety regulations of the hall owner.

9. We undertake to carry out the construction in strict accordance with the approved drawings. If the construction does not conform to the drawings, we will stop the construction, observe and implement the rectification requirements of the lifting point service provider.

10. If the lifting points cannot be used due to our violation of the Exhibitor Manual of China International Import Expo and other relevant safety regulations of the hall owner, we will bear the cost of the lifting points and equipment applied for.

 

Article 3 Responsibility for Construction Safety Accident

We undertake to take responsibility for any personal injury or death, safety production accident and other accidents due to our improper design or improper operation of our personnel on the site, including any third party safety accident, in the process of applying for and using the lifting point service, and at the same time, we will make compensation for the losses caused to the hall owner; If a major safety production accident is caused and the punishment is administered by the relevant administrative departments, we will also bear the corresponding responsibility.

 

Article 4 Others

This undertaking made by us shall be legally binding on us.

This undertaking is in triplicate, with two copies retained by the hall owner and one copy retained by us.

 

Undertaker (official seal): Person in charge of safety:

Legal representative or entrusted agent: mm/dd/yy